The work is progressing according to plan, even with increased focus on Covid-19 at the site for the chemical industry of Solvay in Rheinberg.
We have started up in safe working set-up after the New Year. This is agreed between Solvay and AET in order to secure progress. However, it is not a regulatory requirement.
The collaboration with the customer's representatives on the site works well, and there is a really good atmosphere on the site.
AET site people and our suppliers are finalising minor erection and insulation work. The cold commissioning proceeds according to the project schedule.